IDOT BID ITEMS (Switch to TOLLWAY)
?payitem=54003000
Pay Item # | Pay Item Description | Unit | Quantity | Award Unit Price | County | Dist | Contract | Date | Bid Unit Prices: |
---|---|---|---|---|---|---|---|---|---|
54003000 | CONCRETE BOX CULVERTS | CU YD | 11 | $1,500.00 | LASALLE | 3 | 66L27 | 09/18/2020 | $1,500.00, $3,500.00, $2,300.00, $2,500.00, $2,050.00, $2,650.00 |
54003000 | CONCRETE BOX CULVERTS | CU YD | 234 | $850.00 | MERCER | 4 | 89719 | 07/31/2020 | $850.00, $684.23, $955.00, $875.00, $1,225.00 |
54003000 | CONCRETE BOX CULVERTS | CU YD | 530.100 | $623.00 | JERSEY | 8 | 76568 | 07/31/2020 | $623.00, $1,495.51, $730.00, $1,750.00 |
54003000 | CONCRETE BOX CULVERTS | CU YD | 20.400 | $650.00 | COOK | 1 | 62J28 | 06/12/2020 | $2,770.00, $2,600.00, $650.00 |
54003000 | CONCRETE BOX CULVERTS | CU YD | 38.900 | $1,525.03 | JACKSON | 9 | 78709 | 06/12/2020 | $1,525.03, $1,000.00 |
54003000 | CONCRETE BOX CULVERTS | CU YD | 132.800 | $1,108.48 | SANGAMON | 6 | 93714 | 06/12/2020 | $1,370.93, $1,100.00, $1,108.48, $1,800.00, $1,630.17 |
54003000 | CONCRETE BOX CULVERTS | CU YD | 133.200 | $850.00 | FAYETTE | 7 | 95873 | 06/12/2020 | $850.00 |
54003000 | CONCRETE BOX CULVERTS | CU YD | 120 | $850.00 | BUREAU | 3 | 87720 | 06/12/2020 | $900.00, $850.00, $911.00, $798.31, $725.00, $1,185.00, $1,050.00 |
54003000 | CONCRETE BOX CULVERTS | CU YD | 6.600 | $7,452.80 | DOUGLAS | 5 | 70D74 | 06/12/2020 | $7,452.80 |
54003000 | CONCRETE BOX CULVERTS | CU YD | 16.400 | $3,990.00 | CLINTON | 8 | 76L17 | 06/12/2020 | $3,990.00, $3,300.00 |
54003000 | CONCRETE BOX CULVERTS | CU YD | 10.700 | $3,398.73 | JOHNSON | 9 | 99638 | 06/12/2020 | $3,398.73, $2,200.00, $3,334.00 |
54003000 | CONCRETE BOX CULVERTS | CU YD | 11.100 | $2,250.00 | COOK | 1 | 62J17 | 04/24/2020 | $6,265.00, $3,500.00, $2,000.00, $2,250.00 |
54003000 | CONCRETE BOX CULVERTS | CU YD | 17.300 | $2,700.00 | MCHENRY | 1 | 62D36 | 04/24/2020 | $2,700.00, $2,700.00, $2,419.88, $2,700.00 |
54003000 | CONCRETE BOX CULVERTS | CU YD | 31.400 | $2,500.00 | WILL | 1 | 60V40 | 04/24/2020 | $2,500.00, $1,100.00, $3,300.00, $1,900.00, $1,500.00 |
54003000 | CONCRETE BOX CULVERTS | CU YD | 14.100 | $2,570.00 | DUPAGE | 1 | 61G06 | 04/24/2020 | $4,620.00, $2,570.00, $1,500.00, $1,550.00, $2,982.70 |
54003000 | CONCRETE BOX CULVERTS | CU YD | 106.600 | $850.00 | WILL | 1 | 62G85 | 04/24/2020 | $1,850.00, $900.00, $900.00, $850.00, $1,700.00 |
54003000 | CONCRETE BOX CULVERTS | CU YD | 294.800 | $1,746.62 | FULTON | 4 | 68C64 | 03/06/2020 | $1,746.62, $1,532.69 |
54003000 | CONCRETE BOX CULVERTS | CU YD | 93.800 | $880.00 | BUREAU | 3 | 87719 | 03/06/2020 | $1,100.00, $880.00, $1,000.00, $1,100.00, $888.00, $1,312.00, $1,110.00 |
54003000 | CONCRETE BOX CULVERTS | CU YD | 160.900 | $880.00 | WABASH | 7 | 95869 | 03/06/2020 | $880.00, $800.00 |
54003000 | CONCRETE BOX CULVERTS | CU YD | 353.900 | $1,300.00 | COOK | 1 | 62G92 | 03/06/2020 | $900.00, $1,300.00, $975.00, $775.00 |