IDOT Bid Items
Pay Item # | Pay Item Description | Unit | Quantity | Award Unit Price | County | Dist | Contract | Date | Bid Unit Prices: |
---|---|---|---|---|---|---|---|---|---|
50200300 | COFFERDAM EXCAVATION | CU YD | 96 | $88.00 | SANGAMON | 6 | 93809 | 08/02/2024 | $88.00, $163.33, $80.83, $120.00 |
50200300 | COFFERDAM EXCAVATION | CU YD | 652 | $59.00 | MCHENRY | 1 | 61J93 | 08/02/2024 | $81.25, $74.92, $14.69, $50.00, $59.00 |
50200300 | COFFERDAM EXCAVATION | CU YD | 160 | $75.62 | SANGAMON | 6 | 93654 | 06/14/2024 | $113.79, $75.62, $275.00 |
50200300 | COFFERDAM EXCAVATION | CU YD | 171 | $90.00 | COOK | 1 | 60J10 | 06/14/2024 | $90.00, $200.00, $200.00 |
50200300 | COFFERDAM EXCAVATION | CU YD | 102 | $50.00 | LASALLE | 3 | 66K85 | 06/14/2024 | $50.00 |
50200300 | COFFERDAM EXCAVATION | CU YD | 542.300 | $75.00 | DEKALB | 3 | 87722 | 06/14/2024 | $75.00, $90.00, $88.00, $60.00 |
50200300 | COFFERDAM EXCAVATION | CU YD | 320 | $73.42 | JEFFERSON | 9 | 78885 | 06/14/2024 | $73.42, $75.00 |
50200300 | COFFERDAM EXCAVATION | CU YD | 172 | $95.00 | DUPAGE | 1 | 60P75 | 04/26/2024 | $1.00, $0.01, $70.00, $0.01, $95.00, $95.00 |
50200300 | COFFERDAM EXCAVATION | CU YD | 110 | $50.00 | WILL | 1 | 61H34 | 04/26/2024 | $50.00, $1.00, $164.75, $45.00 |
50200300 | COFFERDAM EXCAVATION | CU YD | 100 | $65.00 | PIKE | 6 | 93815 | 03/08/2024 | $65.00, $61.00, $99.63 |
50200300 | COFFERDAM EXCAVATION | CU YD | 129 | $210.00 | LAKE | 1 | 61J99 | 03/08/2024 | $210.00, $90.00, $85.00, $230.00 |
50200300 | COFFERDAM EXCAVATION | CU YD | 9,146 | $35.00 | WHITE | 9 | 78057 | 03/08/2024 | $17.87, $35.00 |
50200300 | COFFERDAM EXCAVATION | CU YD | 1,347 | $36.00 | MADISON | 8 | 76H49 | 03/08/2024 | $68.70, $115.00, $36.00 |
50200300 | COFFERDAM EXCAVATION | CU YD | 1,890 | $61.00 | WINNEBAGO | 2 | 64K73 | 11/17/2023 | $61.00, $60.00, $50.00, $124.85 |
50200300 | COFFERDAM EXCAVATION | CU YD | 1,132 | $0.01 | MCHENRY | 1 | 61J79 | 11/17/2023 | $70.00, $0.01, $60.00, $68.00, $60.00 |
50200300 | COFFERDAM EXCAVATION | CU YD | 340 | $1.00 | LAWRENCE | 7 | 74359 | 09/22/2023 | $39.15, $1.00 |
50200300 | COFFERDAM EXCAVATION | CU YD | 1,161 | $130.00 | STARK | 4 | 68698 | 08/04/2023 | $130.00 |
50200300 | COFFERDAM EXCAVATION | CU YD | 302 | $58.24 | POPE | 9 | 78792 | 06/16/2023 | $58.24, $100.00 |
50200300 | COFFERDAM EXCAVATION | CU YD | 96 | $46.39 | WAYNE | 7 | 74651 | 06/16/2023 | $46.39, $80.00 |
50200300 | COFFERDAM EXCAVATION | CU YD | 1,305 | $90.00 | MACON | 7 | 95912 | 04/28/2023 | $90.00, $139.45, $200.00 |