IDOT Bid Items (Switch to Illinois Tollway)
/biditem/result/idotplot?payitem=50104720
Pay Item # | Pay Item Description | Unit | Quantity | Award Unit Price | County | Dist | Contract | Date | Bid Unit Prices: |
---|---|---|---|---|---|---|---|---|---|
50104720 | REMOVAL OF EXISTING CONCRETE DECK | EACH | 1 | $234,000.00 | EFFINGHAM | 7 | 74A13 | 06/16/2023 | $234,000.00, $167,434.49 |
50104720 | REMOVAL OF EXISTING CONCRETE DECK | EACH | 1 | $600,000.00 | COOK | 1 | 62H52 | 06/16/2023 | $600,000.00, $1,708,131.00, $2,672,745.51 |
50104720 | REMOVAL OF EXISTING CONCRETE DECK | EACH | 1 | $275,138.40 | CLARK | 7 | 74842 | 04/28/2023 | $275,138.40, $225,000.00 |
50104720 | REMOVAL OF EXISTING CONCRETE DECK | EACH | 1 | $207,687.91 | DUPAGE | 1 | 62K77 | 01/20/2023 | $142,919.35, $150,000.00, $207,687.91 |
50104720 | REMOVAL OF EXISTING CONCRETE DECK | EACH | 1 | $232,413.63 | LOGAN | 6 | 72K64 | 01/20/2023 | $232,413.63 |
50104720 | REMOVAL OF EXISTING CONCRETE DECK | EACH | 1 | $235,715.00 | FAYETTE | 7 | 74983 | 11/18/2022 | $235,715.00, $448,066.92 |
50104720 | REMOVAL OF EXISTING CONCRETE DECK | EACH | 1 | $250,000.00 | LAKE | 1 | 62P14 | 06/17/2022 | $257,232.00, $566,000.00, $250,000.00, $250,000.00 |
50104720 | REMOVAL OF EXISTING CONCRETE DECK | EACH | 1 | $150,000.00 | COOK | 1 | 62P10 | 04/29/2022 | $531,000.00, $185,000.00, $455,000.00, $437,275.00, $267,200.19, $325,000.00, $150,000.00 |
50104720 | REMOVAL OF EXISTING CONCRETE DECK | EACH | 1 | $34,000.00 | ST. CLAIR | 8 | 97752 | 03/11/2022 | $34,000.00, $33,750.00 |
50104720 | REMOVAL OF EXISTING CONCRETE DECK | EACH | 1 | $105,861.94 | CHRISTIAN | 6 | 72A26 | 03/11/2022 | $107,024.65, $105,861.94, $125,000.00 |
50104720 | REMOVAL OF EXISTING CONCRETE DECK | EACH | 1 | $95,036.18 | LAWRENCE | 7 | 74440 | 01/21/2022 | $95,036.18 |
50104720 | REMOVAL OF EXISTING CONCRETE DECK | EACH | 1 | $139,200.00 | STEPHENSON | 2 | 64N03 | 01/21/2022 | $139,200.00, $200,000.00, $175,000.00 |
50104720 | REMOVAL OF EXISTING CONCRETE DECK | EACH | 1 | $80,626.12 | ADAMS | 6 | 72L62 | 11/05/2021 | $80,000.00, $80,626.12 |
50104720 | REMOVAL OF EXISTING CONCRETE DECK | EACH | 1 | $154,000.00 | OGLE | 2 | 64L75 | 09/17/2021 | $475,000.00, $154,000.00, $150,000.00, $326,250.00, $160,000.00, $177,767.84, $122,532.98 |
50104720 | REMOVAL OF EXISTING CONCRETE DECK | EACH | 1 | $110,000.00 | COOK | 1 | 62K80 | 04/23/2021 | $267,880.00, $110,000.00, $428,000.00, $197,250.00, $300,000.00, $250,000.00 |
50104720 | REMOVAL OF EXISTING CONCRETE DECK | EACH | 1 | $223,000.00 | GRUNDY | 3 | 66E45 | 01/15/2021 | $105,000.00, $450,000.00, $313,778.25, $223,000.00 |
50104720 | REMOVAL OF EXISTING CONCRETE DECK | EACH | 2 | $186,611.24 | MONTGOMERY | 6 | 72D31 | 06/12/2020 | $186,611.24 |
50104720 | REMOVAL OF EXISTING CONCRETE DECK | EACH | 1 | $95,000.00 | HANCOCK | 6 | 93746 | 06/12/2020 | $95,000.00, $150,000.00 |
50104720 | REMOVAL OF EXISTING CONCRETE DECK | EACH | 1 | $37,996.79 | LOGAN | 6 | 93738 | 04/24/2020 | $82,200.00, $89,519.04, $98,000.00, $37,996.79 |
50104720 | REMOVAL OF EXISTING CONCRETE DECK | EACH | 1 | $135,000.00 | IROQUOIS | 3 | 87548 | 01/17/2020 | $130,000.00, $135,000.00 |