IDOT Bid Items (Switch to Illinois Tollway)
/biditem/result/idotplot?payitem=50100300
Pay Item # | Pay Item Description | Unit | Quantity | Award Unit Price | County | Dist | Contract | Date | Bid Unit Prices: |
---|---|---|---|---|---|---|---|---|---|
50100300 | REMOVAL OF EXISTING STRUCTURES NO. 1 | EACH | 1 | $150,000.00 | VERMILION | 5 | 70860 | 08/04/2023 | $319,000.00, $212,065.94, $150,000.00 |
50100300 | REMOVAL OF EXISTING STRUCTURES NO. 1 | EACH | 1 | $75,000.00 | CHAMPAIGN | 5 | 70581 | 06/16/2023 | $75,000.00, $150,950.00 |
50100300 | REMOVAL OF EXISTING STRUCTURES NO. 1 | EACH | 1 | $20,000.00 | OGLE | 2 | 64F57 | 06/16/2023 | $20,000.00 |
50100300 | REMOVAL OF EXISTING STRUCTURES NO. 1 | EACH | 1 | $60,000.00 | CHRISTIAN | 6 | 72984 | 06/16/2023 | $60,000.00 |
50100300 | REMOVAL OF EXISTING STRUCTURES NO. 1 | EACH | 1 | $7,482.64 | FRANKLIN | 9 | 78915 | 06/16/2023 | $14,084.67, $8,000.00, $7,482.64 |
50100300 | REMOVAL OF EXISTING STRUCTURES NO. 1 | EACH | 1 | $40,000.00 | VARIOUS | 1 | 62P71 | 06/16/2023 | $40,000.00, $82,870.00, $15,567.82, $58,125.00, $235,189.74 |
50100300 | REMOVAL OF EXISTING STRUCTURES NO. 1 | EACH | 1 | $300,000.00 | WINNEBAGO | 2 | 64B13 | 06/16/2023 | $300,000.00, $1,790,198.20, $406,273.62 |
50100300 | REMOVAL OF EXISTING STRUCTURES NO. 1 | EACH | 1 | $10,000.00 | JOHNSON | 9 | 78524 | 06/16/2023 | $10,751.78, $10,000.00 |
50100300 | REMOVAL OF EXISTING STRUCTURES NO. 1 | EACH | 1 | $10,260.50 | JACKSON | 9 | 78790 | 06/16/2023 | $10,260.50, $12,000.00 |
50100300 | REMOVAL OF EXISTING STRUCTURES NO. 1 | EACH | 1 | $175,000.00 | MACON | 7 | 95912 | 04/28/2023 | $175,000.00, $136,459.03, $200,000.00 |
50100300 | REMOVAL OF EXISTING STRUCTURES NO. 1 | EACH | 1 | $328,325.00 | WILL | 1 | 62P67 | 04/28/2023 | $328,325.00, $225,000.00, $688,841.20, $570,000.00 |
50100300 | REMOVAL OF EXISTING STRUCTURES NO. 1 | EACH | 1 | $39,000.00 | VERMILION | 5 | 70840 | 04/28/2023 | $39,000.00, $41,000.00 |
50100300 | REMOVAL OF EXISTING STRUCTURES NO. 1 | EACH | 1 | $30,000.00 | MONTGOMERY | 6 | 93778 | 03/10/2023 | $30,000.00, $67,000.00, $44,000.00 |
50100300 | REMOVAL OF EXISTING STRUCTURES NO. 1 | EACH | 1 | $150,000.00 | LASALLE | 3 | 87673 | 01/20/2023 | $150,000.00, $500,000.00 |
50100300 | REMOVAL OF EXISTING STRUCTURES NO. 1 | EACH | 1 | $55,000.00 | WHITE | 9 | 78682 | 01/20/2023 | $55,000.00, $100,000.00 |
50100300 | REMOVAL OF EXISTING STRUCTURES NO. 1 | EACH | 1 | $169,193.53 | SALINE | 9 | 78716 | 01/20/2023 | $169,193.53, $550,000.00 |
50100300 | REMOVAL OF EXISTING STRUCTURES NO. 1 | EACH | 1 | $445,000.00 | LAKE | 1 | 62A53 | 01/20/2023 | $122,475.00, $445,000.00, $1,270,000.00, $1,953,700.00, $535,000.00, $550,000.00 |
50100300 | REMOVAL OF EXISTING STRUCTURES NO. 1 | EACH | 1 | $42,000.00 | MACOUPIN | 6 | 72B64 | 11/18/2022 | $53,980.00, $42,000.00 |
50100300 | REMOVAL OF EXISTING STRUCTURES NO. 1 | EACH | 1 | $7,141.31 | FRANKLIN | 9 | 78893 | 11/18/2022 | $11,793.03, $8,500.00, $7,141.31 |
50100300 | REMOVAL OF EXISTING STRUCTURES NO. 1 | EACH | 1 | $750,000.00 | DUPAGE | 1 | 61G82 | 11/18/2022 | $220,000.00, $750,000.00, $1,475,000.00, $726,000.00, $870,000.00, $2,700,000.00, $2,400,000.00 |